Installation and Assembly - Switch Electric Fireplaces 1

Dimensions and Specifications

ModelViewing
Area
Firebox
Dimensions
Framing
Dimensions
Switch 4443 1/4” W x 15 7/8” H x 5 5/16” D43 1/4” W x 15 7/8” H x 5 5/16” D44 1/16” W x 24 7/8” H x 11 9/16” D44 1/16” W x 24 7/8” H x 11 9/16” D44 3/8” W x 25 1/4” H x 12” D44 3/8” W x 25 1/4” H x 12” D
Switch 56 55 1/4” W x 15 7/8” H x 5 5/16” D55 1/4” W x 15 7/8” H x 5 5/16” D56 1/16” W x 24 7/8” H x 11 9/16” D56 1/16” W x 24 7/8” H x 11 9/16” D56 3/8” W x 25 1/4” H x 12” D56 3/8” W x 25 1/4” H x 12” D
Switch 6867 1/4” W x 15 7/8” H x 5 5/16” D67 1/4” W x 15 7/8” H x 5 5/16” D68 1/16” W x 24 7/8” H x 11 9/16” D68 1/16” W x 24 7/8” H x 11 9/16” D68 3/8” W x 25 1/4” H x 12” D68 3/8” W x 25 1/4” H x 12” D
Switch 8079 1/4” W x 15 7/8” H x 5 5/16” D79 1/4” W x 15 7/8” H x 5 5/16” D80 1/16” W x 24 7/8” H x 11 9/16” D80 1/16” W x 24 7/8” H x 11 9/16” D80 3/8” W x 25 1/4” H x 12” D80 3/8” W x 25 1/4” H x 12” D
Switch 9695 1/4” W x 15 7/8” H x 5 5/16” D95 1/4” W x 15 7/8” H x 5 5/16” D96 1/16” W x 24 7/8” H x 11 9/16” D96 1/16” W x 24 7/8” H x 11 9/16” D96 3/8” W x 25 1/4” H x 12” D96 3/8” W x 25 1/4” H x 12” D
Switch 120119 1/4” W x 15 7/8” H x 5 5/16” D119 1/4” W x 15 7/8” H x 5 5/16” D120 1/16” W x 24 7/8” H x 11 9/16” D120 1/16” W x 24 7/8” H x 11 9/16” D120 3/8” W x 25 1/4” H x 12” D120 3/8” W x 25 1/4” H x 12” D

Installation Location

Your appliance is a wall-mounted, recessed, and/or mantel installed appliance. Select a suitable location that is not susceptible to moisture and is away from drapes, furniture, and high traffic areas.

NOTE: Follow all National and local electrical codes.

This product includes a GLASS panel. Always use extreme caution when handlingglass. Failure to do so could result in personal injury or property damage.

Due to the many different materials used on different walls, it is highly recommended that you consult your local builder before you install this fireplace.

Remove all parts and hardware from the carton and place them on a clean, soft, dry surface. Parts and assembly steps are grouped for use. Check the parts list to make sure nothing is missing. Dispose of packaging materials properly. Please recycle whenever possible.

You will need the following tools (not included):
Phillips screwdriver, stud finder, level, tape measure, electric drill, 1/4” wood drill bit, hammer.

Built-in Installation

Optional Built-In styles shown below. See “Partial Recess Installation” or “Wall Mounted Installation” for additional mounting styles.

Switch Bay (3 Open Sides)

Installation and Assembly - Switch Electric Fireplaces 2

Switch Left Corner (2 Open Sides: Front and Left Corner)

Switch Right Corner (2 Open Sides: Front and Right Corner)

Installation and Assembly - Switch Electric Fireplaces 3

Switch Single Sided (1 Open Side)

Installation and Assembly - Switch Electric Fireplaces 4

Use a dedicated 20 Amp (or higher), 2-pole (for 10,000 BTUs) circuit breaker.

3 Sided Installation (Bay)

1. Prepare the framed opening according to the chart.

*Provide appropriate dedicated circuit for hardwire install at the top right of framed opening.

Installation and Assembly - Switch Electric Fireplaces 5

2. Install L Metal mounting brackets to the top and bottom of the fireplace with supplied screws.

3. Hardwire fireplace (see instructions)

4. Install the fireplace in the framed opening with a minimum 1 1/4” 32 mm drywall screws to secure the unit.

Installation and Assembly - Switch Electric Fireplaces 6

5. Mask the exposed fireplace during the drywall process. Install drywall to the drywall stops on the perimeter of the fire box. For more information on the drywall stops see the Product Guide.

6. Decorate according to media installation guide.

7. Install the side and front glass pieces according to installation diagram.

8. Install optional 5-pc. trim kit (sold separately.)

Installation and Assembly - Switch Electric Fireplaces 7

Fully Recessed Installation (Left/Right Corner)

1. Follow steps from the 3-sided installation instructions.

2. Remove the corresponding drywall stops according to your installation (in the example, the drywall stops on the left end would be removed.)

3. Install the side glass then the corresponding side cover according to your installation (the side glass must be installed before the metal side cover. See installation diagram.)

Installation and Assembly - Switch Electric Fireplaces 8

4. Wire fireplace (see instructions) for maximum heating power (10,000 BTUs) see optional wiring.

5. Install the fireplace in the framed opening with a minimum 1 1/4” 32 mm drywall screws to secure the unit.

6. Mask the exposed fireplace during the drywall process. Install drywall to the drywall stops on the perimeter of the fireplace. For more information on the drywall stops see the Product Guide.

7. Decorate according to media installation guide.

8. Install the remaining side glass and front glass according to installation diagram.

9. Install optional 5-pc. trim kit (sold separately.)

Installation and Assembly - Switch Electric Fireplaces 9

Fully Recessed Installation (Single Sided)

1. Follow steps from the 3 sided installation instructions.

2. Remove the drywall stops on both sides of the fire unit.

3. Install the side glass then side covers on both sides of the fire unit (the side glass must be installed before the metal side cover. See installation diagram.)

4. Install the fire unit in the framed opening with a minimum 1 1/4” 32 mm drywall screws to secure the unit.

Installation and Assembly - Switch Electric Fireplaces 10

5. Mask the exposed fireplace during the drywall process. Install drywall to the drywall stops on the perimeter of the fireplace. For more information on the drywall stops see the Product Guide.

6. Decorate according to media installation guide.

7. Install the front glass according to installation diagram.

8. Installation optional: 1-pc trim kit (included.)

Installation and Assembly - Switch Electric Fireplaces 11

Half Recessed Installation

1. This installation is optimized for a 2x4 framed wall. Prepare the framed opening according to the height and width of the chart.

*Provide appropriate dedicated circuit for hardwire install at the top right of framed opening.

Installation and Assembly - Switch Electric Fireplaces 12

2. Install L Metal Nailing Flanges to the top and bottom of the fireplace.

3. Hardwire fireplace (see instructions).

4. Install the fire unit in the framed opening with a minimum 1 1/4” 32 mm drywall screws to secure the unit.

Installation and Assembly - Switch Electric Fireplaces 13

5. Mask the exposed viewing area of fireplace during this process. Install drywall, tile or material of your choice to the drywall stops on the perimeter of the fireplace. For more information on the drywall stops see the Product Guide.

6. Decorate according to media installation guide.

7. Install the side and front glass pieces according to installation diagram.

8. Finish fireplace with your desired decorative.

Installation and Assembly - Switch Electric Fireplaces 14

Outdoor Installation Requirements

The Switch Electric Series have been tested and approved for installation outdoors under a patio cover and away from direct water contact or direct sun light.

Switch Electric Series standard warranty applies if installed per instructions. All electrical wiring shall be to local building codes. Consult professional installers before installation. Approved installations are as noted below.

Front Protection

Patio roof overhang must be 50% (or more) of the height of the patio roof from bottom of fireplace.

If: H=6’

Then: OD=3’ minimum (6’ x 50%=3’)

Note 1: Base of fireplace must be 2” (minimum) above floor.

Note 2: H taken from bottom of fireplace.

Installation and Assembly - Switch Electric Fireplaces 15

Side Protection

Side distance (SD) must be 50% (or more) of the height(H).

If: H=6’

Then: SD=3’ minimum (6’ x 50%=3’)

Note: H taken from bottom of fireplace.

Installation and Assembly - Switch Electric Fireplaces 16